(tried to find this in the forums, could not)
I have multiple tasks, each a few hours long. If Task A starts at 8am and runs 4 hours the calculated duration is 8am - 12pm. Great. Now I add Task B, which is where I’m confused.
If Task B:
- is set to be “blocked by” Task A as “finish to start” (meaning, Task B will begin when Task A finishes)
- and Task B is set to be 4 hours duration
- I would expect that the combined duration of Task A and Task B is 8 hours on a single day.
However, what Timeline presents is that Task A begins at 8am on Day One and, on the following day, Task B starts at 8am. My expectation would be:
- Task A: 8am - 12pm
- Task B: 12pm - 4pm
Is there a way to set work hours and the expectation that a task be started but not necessarily finished on the same day? I would expect the ability to set duration of work days and which days of the week are working days.
Thanks in advance for help and guidance.